Aurizon Inner and Outer Fort Roads Upgrade

Demolition and replacement of 292m of rail track and slab. The works were in the NSS operating area at Berth 3 and included:
• Demolition of the existing slab
• Excavation, testing and compaction of base
• Concrete: 50mm blinder, 300mm S40 base slab, 200mm S50 upper slab.
• Rail placement.
• Line-marking